West Norriton Township has awarded the 2017 Road Paving Project to Joseph E. Sucher & Sons to mill and pave streets in the township.
The work will be performed from Friday, October 20th thru Wednesday, October 25th.
Please remove all vehicles from the street by 7:00 AM. Please see the attached notice for more information.
On Friday, October 20th, the following streets will be milled:
- Harrow Circle
- Wagon Wheel Road
- Dairy Lane
- Stable Road
- Horshoe Road (partial)
- S. Montgomery Avenue
The following streets will be paved on Monday, October 23rd:
- Harrow Circle
- Wagon Wheel Road
- Dairy Lane
The following streets will be paved on Tuesday, October 24th
- Horseshoe Road (partial)
- Stable Road
- S. Montgomery Avenue.
All work is weather dependent.